Updated: 04/27/2021, 09:00
Selezionare un paese per visualizzare i contenuti e i prodotti per quel mercato.
Paese
Lingue disponibili
OKUpdated: 04/27/2021, 09:00
The Gebidem dam and the Bitsch powerhouse are the key elements of Electra-Massa. Commissioned in 1969, these facilities are about two-thirds through their service life. In order to ensure that they function correctly and to maintain them in good condition until the end of the concession in 2048 according to the concession-holder’s obligations, Electra-Massa is undertaking major maintenance and renewal work. The shareholders will invest around CHF 8 million between 2020 and 2022 to carry out this work.
The Gebidem dam was completely drained in October 2020. This step was necessary in order to renovate the bottom valve of the dam and to replace the butterfly valve located downstream of the wall. The anti-corrosion protection of the penstock connecting the dam to the power plant had to be completely renewed. This is complicated and time-consuming work. The old anti-corrosion protection must first be removed and the surface be perfectly clean before the new one can be applied.
The workers also carried out maintenance in the lowlands at the Bitsch powerhouse. They completely overhauled the main valve of machine groupe 3, as well as the transformer.
The first stage of anti-corrosion protection work on the penstock system was completed on schedule at the end of April. The impoundment of the lake could already be started at the end of March, which meant that the power plant could be put back into operation in time for the start of the summer season. However, work will resume next winter to complete the anti-corrosion protection of the penstock and to carry out the annual maintenance work on the powerhouse’s three machine groups.
While the Electra-Massa facility is out of service, Swissgrid, the national transmission grid operator, is taking the opportunity to renew the 220 kV substation at Bitsch, which connects the power plant to the extra-high-voltage transmission grid.
The works underway at Electra-Massa are unique due to their scale and complexity. As asset manager, Alpiq is in charge of the entire project. The company is working closely with HYDRO Exploitation, which is responsible for managing the project and the works.
In addition to the technical aspects related to infrastructure, Electra-Massa attaches great importance to safety and the environment. Anti-corrosion protection work in the penstock, risk of landslides and avalanches, work in the immediate vicinity of the Jungfrau-Aletsch Nature Park, there are numerous challenges – in addition to the restrictions associated with the coronavirus pandemic. For this reason, an environmental office is supervising the work with natural hazard specialists to ensure that the safety and environmental concepts they have developed are being implemented.
Power Plant Manager at Electra-Massa, Hydro Exploitation
In principle, the Gebidem dam is only accessible on foot in winter. However, due to the ongoing work, the access road to the dam had been cleared throughout the winter. If conditions became dangerous, the regional security service, with whom we are working closely, blocked the access and closed the construction site. This was the case, for example, between 28 and 31 January 2021, as a result of the large amount of fresh snow and the mild temperatures that followed. An avalanche buried the two bottom valves of the dam.
We also carefully observed the formation of ice stalactites on the crest of the dam, as some of the work took place just below it.
The work being carried out is far from usual. This is the first time since the commissioning of the facility just over 50 years ago that we have replaced the dam's butterfly valve and renewed the penstock's anti-corrosion protection. We didn't know the exact condition that the facilities were going to be in. We were constantly faced with unforeseen events that had to be overcomed.
With different works taking place at the same time, it was essential to plan them carefully in advance. Good communication and flexibility are also necessary because there were a lot of companies involved.
One of the biggest challenges, however, was draining Lake Gebidem. Because of the small amount of water in the Rhône, and because the waters of Lake Gebidem are very heavily laden with sediment, we had to pay particular attention to the concentration of suspended matter. Nevertheless, we managed to drain the lake while meeting all the specifications.
In addition to the technical aspects, it had also been important to keep an eye on developments in the COVID-19 pandemic and the possible impact on ongoing work.
For me, Electra-Massa is not just a power plant, it is located in the middle of the mountains where I grew up. I discovered the watershed of Lake Gebidem, with the great Altesch Glacier and the Oberaletsch Glacier, as well as the Massa Gorge when I was a young boy.
Electra-Massa is an efficient and interesting power plant right on my doorstep. I am very proud and happy to be working for this facility.